Termination on rejection of an activity (release process)

If a parallel subprocess is to be aborted when a certain number of activities have been rejected, then the % threshold of the subprocess control must be set to what percentage of the activities must be completed positively.

The mode must be set to "Consider all status" or to "Consider all status, optimistic".

If no activity may be negative, 100% must be set as the % threshold.

With a threshold of 100%, the options "Consider all status" as well as "Consider all status, optimistic" are equivalent.