Production Order / Process Order

If relevant, the F4 search help for the "Revision level" field shows the plant revisions. See .

Write plant revision initial

The plant revision is determined on the basis of the explosion date of the production order. The explosion date of the bill of material is used, not the explosion date of the plan. The determined plant revision is written into the field "Revision level" of the production order.

The explosion date can be in the past or in the future.

The plant revision must be released on this date (currently valid or planned revision).

Write plant revision at “Read master data”

When the "Read PP master data" function is executed, the plant revision is determined and written again according to the above rules.

Document linking

Depending on the settings, documents can also be automatically linked to the production order, see .